Do I need a permit for a deck, shed, fence or pool in Mississauga, Ontario?

Mississauga, Ontario, Canada

When Mississauga homeowners need a building permit for a deck, shed or gazebo, fence height rules, pool enclosure approval, fees from $244 and review times.

Key information

In Mississauga you need a building permit for a deck higher than 0.61 m (2 feet), a shed over 15 square metres or any shed with plumbing, and a gazebo over 10 square metres. Most fences need no permit but must meet height limits, and every pool or hot tub needs City approval and an enclosure inspection before it is filled.

Mississauga Civic Centre with its clock tower, seen across the lawn of the civic square
Mississauga Civic Centre (City Hall) at 300 City Centre Drive, May 11, 2009. Photo: Visnja, Wikimedia Commons (CC BY-SA 2.0), Source website.
On this page

At a glance

Common backyard projects in Mississauga, checked November 18, 2026.
ProjectPermit needed?Rule from the City
DeckYes if higher than 0.61 m (2 ft)Decks under 600 mm need no building permit
ShedYes if over 15 m2 or it has plumbingOne-storey storage sheds under 15 m2 without plumbing need no permit
GazeboYes if over 10 m210 m2 or less needs no permit
Covered porchYesListed as needing a permit
FenceNo building permitMust meet Fence By-law heights; exemption costs $361.20
Retaining wallYes if 1 m or higherUnder 1 m needs no permit
Pool, hot tub or swim spaCity approval and inspection$402.53 enclosure inspection fee plus deposits

Sources: City of Mississauga: When a building permit is required · City of Mississauga: Fences · City of Mississauga: Swimming pool installation

How much does a building permit cost and how long does it take?

Average total time to get a permit, by project type, from the City's cost and time frames page.
  • Residential alteration7 weeks
  • Second unit10 weeks
  • New house (detached or semi)13 weeks

A residential building permit costs at least $244. You pay a $50 non-refundable administrative fee when you submit online through ePlans, and it is credited toward the permit. The exact fee is set after prescreening using the Building Permit Fee Schedule.

Prescreening usually takes 7 to 10 business days. A complete residential application then gets its first review in about 10 business days. On average, a residential alteration takes about 7 weeks from start to permit. Each resubmission can add two or more weeks.

Sources: City of Mississauga: Building permit cost and time frames

How high can my fence be?

To build a fence that breaks these rules, apply for a fence exemption ($361.20 including HST) with a survey, site plan, fence details and at least two photos. The City notifies neighbours who share your property line. Disputes about shared boundary fences are settled between neighbours under the Line Fences Act; the City does not get involved.

  • Back or side yard: up to 2 metres high.
  • Front yard: up to 1 metre, or 1.5 metres if it is open construction (at least one-third see-through).
  • If your backyard is next to a neighbour's front yard, the fence must be open construction within 4.5 metres of their driveway.
  • No fences on City property or road allowances, and no barbed wire or hazardous material on residential land.
  • Corner lots and sight triangles have extra rules in the Fence By-law.

Sources: City of Mississauga: Fences

What do I need before installing a pool or hot tub?

Properties on conservation land also need written permission from the conservation authority. If landscaping is not finished at the grading inspection, you pay a $300 plus HST re-inspection fee.

  1. Read the City's Swimming Pool and Hot Tub Installation Guide and check zoning setbacks.
  2. Submit an 11 x 17 inch scaled site plan with lot grading, a legal survey, a signed statutory declaration and a pool enclosure inspection request, with the $402.53 inspection fee. Submit in person by appointment or by mail to 950 Burnhamthorpe Road West.
  3. After approval, pay a refundable municipal services deposit ($1,500 for in-ground and on-ground pools, $750 for above-ground pools) plus inspection and administration fees.
  4. Attend a pre-construction meeting at your property with the pool location marked.
  5. Before filling the pool, call 311 for the final enclosure inspection, then for the lot grading inspection once landscaping is done.

Sources: City of Mississauga: Swimming pool installation

How do I apply for a building permit?

Building permit steps in Mississauga
  1. Check

    Confirm your project needs a permit and meets zoning.

  2. Submit

    Create an ePlans account and upload drawings. Pay the $50 fee.

  3. Prescreen

    About 7 to 10 business days, then the exact fee is set.

  4. Review

    About 10 business days for a complete residential application.

  5. Build and inspect

    Book inspections as work goes on.

Sources: City of Mississauga: Building permits · City of Mississauga: Building permit cost and time frames

Questions and answers

Do I need a permit for a deck in Mississauga?

Yes if it is more than 0.61 metres (2 feet) high. Lower decks do not need a permit.

Source: City of Mississauga: When a building permit is required

Do I need a permit for a shed?

Only if it is over 15 square metres or contains plumbing.

Source: City of Mississauga: When a building permit is required

Do I need a permit for a fence?

No building permit is needed, but the fence must follow the Fence By-law.

Source: City of Mississauga: When a building permit is required

How tall can a backyard fence be?

Up to 2 metres.

Source: City of Mississauga: Fences

How tall can a front yard fence be?

1 metre, or 1.5 metres if it is open construction.

Source: City of Mississauga: Fences

How much is a fence exemption?

$361.20 including HST.

Source: City of Mississauga: Fences

What is the minimum cost of a residential building permit?

$244.

Source: City of Mississauga: Building permit cost and time frames

How long does a permit take for a home renovation?

On average about 7 weeks for a residential alteration.

Source: City of Mississauga: Building permit cost and time frames

What does a pool enclosure inspection cost?

$402.53 including HST, plus deposits and other fees.

Source: City of Mississauga: Swimming pool installation

When do I book the final pool inspection?

Before you fill the pool for the first time. Call 311.

Source: City of Mississauga: Swimming pool installation

Official permit pages

The City's pool page lists non-refundable inspection fees of $297.19 for on-ground pools, hot tubs or spas and $593.25 for above-ground pools, plus a $33.90 administrative fee. Confirm the amount for your pool type with the City.

Get in touch
My Mississauga